General Information
- RFAAP Environmental Policy (Current)
- Community Relations Plan
(Sept 5, 1995)—Includes
an overview of the site history and community background, description
of the community relations program including communication activities,
and points of contact.
- Fact sheets
- U.S.
Army Industrial Operations Command
(Sept 1997)
- Restoration
Advisory Board
(Revised 2001)
- Information
Repository
(July 1999) (Filed with July 1999 RAB minutes/handouts)
- IRP
Status Report Update (Updated
May 2000) (Filed with May
2000 RAB minutes/handouts)
- IRP
Status Report Update (Updated
July 2000) (Filed with July 2000 RAB minutes/handouts)
- IRP
Status Report Update (Updated
November 2000) (Filed with November 2000 RAB minutes/handouts)
- Geophysical
Survey Methods Used… (September
2002) (Filed with September 2002 RAB minutes/handouts)
- Cleanup
Program at the Radford Army Ammunition Plant
(January 2002)
- Frequently
Asked Questions (May
2002)
- IRP
Status Report Update (November
2002)
- News clippings and news releases
- RAAP wants citizen involvement:
Membership on advisory board would give insight into cleanup
efforts (New River Newspapers)
- Arsenal seeking citizen input
on cleanup (The Roanoke Times, February 27, 1998)
- Arsenal seeking input: RAAP
considers Restoration Advisory Board (New
River Newspapers, March 4, 1998)
- Radford plant is ‘one of kind:’
Army will close ammo facilities; RAAP is not on closure list
(New River Newspapers,
June 20, 1998)
- RAAP starts restoration effort:
Partnership with community emphasized for environmental cleanup
(New River Newspapers,
September 12, 1998)
- News Release: Restoration Advisory
Board (February 1998)
- News Release: Radford Army Ammunition
Plant announces its new web site for the Installation Restoration
Program (April 2000)
- Local plant announces new web
site (The Southwest Times, April 12, 2000)
- News Release: Radford Army Ammunition
Plant invites community members to join its Restoration Advisory
Board (June 2000)
- Ammunition
plant seeks board members (The
Southwest Times, June 29, 2000)
- Restoration Advisory Board (RAB)
mission statement and charter
- RAB meeting agendas, minutes, and
handouts
Documents
- Verification Investigation:
Volumes I, II and III (Final Draft, October 29, 1992). The object
of a Verification Investigation (VI) is to evaluate whether toxic
or hazardous contaminants are present and are, or have the potential
of, migrating beyond the boundaries of the identified sites (Solid
Waste Management Units, SWMUs) by investigating the nature and
extent of hazardous constituents in surface water, ground water,
soil, and sediment.
- Verification Investigation
- Revised Section 7.0, SWMUs 10 and 35 (Draft, September
8, 1994)
- Revised Section 9.0, SWMUs 27, 29, and 53 (Draft,
August 19, 1994)
- Revised Section 11.0, SWMU 39, Incinerator Wastewater
Ponds (Draft August 31, 1994)
- Revised Section 24.0, SWMU 71, Flash Burn Parts Area
(Draft, August 19, 1994)
- RCRA Facility Investigation: Volumes I, II, and III
(Final Draft, October 29, 1992). The general purpose of a RCRA
Facility Investigation (RFI) is to characterize the nature, extent,
direction, rate, movement, and concentration of contaminant releases,
determine the potential need for corrective measures, and aid
in selection and implementation of those measures.
- RCRA Facility Investigation Revised Section 8.0, SWMU O,
Underground Fuel Oil Spill (Draft, September 16, 1994)
- Supplemental RFI Report for SWMU 54 (Draft, January
20, 1999) & U.S. Environmental Protection Agency comments
dated March 16, 1999
- Closure Report, SWMU 69, Pond by Chromic Acid Treatment
Tanks (Draft, August 30, 1994) – outlines the measures taken
to remove the impacted sediment and soil at SWMU 69 and subsequently
close the site upon agency approval.
- Closure Report for the Eastern Lagoon of SWMU 8 – summarizes
the activities undertaken during the Interim Remedial Action at
SWMU 8 Eastern Basin and presents the results of these activities
in support of final closure of the Eastern Basin.
- Closure Documentation for Solid Waste Management Unit 10
Biological Treatment Plant Equalization Basin: Volumes 1 and
2
- Screening Ecological Risk Assessment (Draft, September
1999) – assesses the potential for adverse effects to non-human
receptors resulting from exposure to chemicals at the Main Section
of the RFAAP.
- Master Work Plan, Quality Assurance Plan, Health and Safety
Plan, Addendum 010: Facility-Wide Background Study (Final
Document, September 2000)
- Master Work Plan, Quality Assurance Plan, Health and Safety
Plan, Addendum 011: Soil Sampling and Reporting at SWMU 6 (Final
Document, November 2000)
- RCRA Permit for Corrective Action and Waste Minimization
(October 2000) - includes terms and conditions for
the management of described hazardous waste, investigation of
Site Screening Areas, and other related requirements.
- RCRA Facility Assessment of Radford Army Ammunition Plant
(USATHAMA, 1987) - identifies information on solid waste management
units and other areas of concern, evaluates the potential for
release to the environment, and determines the need for further
investigation.
- SWMU 6 Decision Document, Final October 2002 – provides
information on soil sampling at SWMU 6, as a part of managing
excavated soils that will be generated as part of the Production
Base Support (PBS) project to construct nitrocellulose (NC) settling
tanks at SWMU 6.
- Work Plan Addendum No. 13, RCRA Facility Investigation at
Solid Waste Management Unit 54 Final Document, September 2002
- Building 4343 RCRA Facility Investigation/Corrective Measures
Study Report, Final Document February 2004 contains data, assessments
and recommendations.
- Installation Action Plan for Radford Army Ammunition Plant ( Fiscal Year 2005) – provides RFAAP site descriptions, overview of past actions and cleanups, restoration schedule, and program.
|