July 19, 2001
Meeting Minutes
Attendance
Members: |
Organization: |
Allen Boynton |
VA Dept of Game & Inland Fisheries |
Steve Cole |
Blacksburg Rotary Club |
Jim McKenna |
RFAAP/RAB Co-Chair |
Joe Parrish |
Anderson & Associates |
|
|
Attendees: |
Organization: |
Rick Cole |
URS Corp. |
Steve Grieco |
WPI |
Elizabeth Lohman |
Virginia Department of Environmental Quality,
WCRO |
Jerry Redder |
Alliant Ammunition and Powder Company/RFAAP |
John Tesner |
U.S. Army Corps of Engineers, Baltimore
District |
Sharon Wilcox |
Virginia Department of Environmental Quality |
Agenda
Item #1. Introductory Remarks
At 6:30, Mr. Jim McKenna gathered those in
attendance to prepare for a site tour. He described the U.S. Environmental
Protection Agency (EPA) Resource Conservation and Recovery Act (RCRA)
Permit for Corrective Action and Waste Minimization (Permit Number
VA1210020730) issued to Alliant Ammunition and Powder Company LLC and the
United States Department of the Army, copies of which will be added to the
RFAAP information repository at the Christiansburg library. The 1987 RCRA
Facility Assessment will also be added to the information repository.
Agenda Item #2. Radford Army Ammunition Plant (RFAAP)
Site Tour
Mr. McKenna and Mr. Jerry Redder led a tour of Site
Screening Area (SSA) sites and structures included RCRA permit. These
sites, listed at the end of these notes, will be screened to determine the
need for further action. RAB members were driven around the RFAAP in a
van. There was frequent discussion about the status of SSA sites and
questions about general facility operations—past, present, and future.
Agenda Item #3. Closing Remarks, Schedule Next
Meeting, Adjourn
Mr. McKenna concluded the tour at 8:30 p.m. Another
site tour—this time for the New River Unit—is planned for the next RAB
meeting, will be held on Thursday, 20 September 2001, at 6:30 p.m.
Site Screening Areas listed in RCRA Corrective
Action Permit VA1210020730
SSA-2 TNT Wastewater Equalization Basin
SSA-3 TNT Wastewater Treatment Unit
SSA-11 Nitroglycerin 1 Pretreatment Unit
SSA-12 Nitroglycerin 2 Pretreatment Plant
SSA-18 Sulfuric Acid Recovery Plant—Waste Acid Treatment
SSA-19 The A-B Line Acidic Wastewater Treatment Plant
SSA-20 C Line Acidic Wastewater Treatment Plant
SSA-21 Continuous Automated Single-Base Wastewater Treatment Plant
SSA-22 Wastewater Holding Lagoons
SSA-23 Wastewater Holding Lagoons
SSA-24 Wastewater Holding Lagoons
SSA-25 Wastewater Holding Lagoons
SSA-30 Asbestos Disposal Trench No. 1
SSA-33 Treatment Plant for Solids from Water Treatment
SSA-34 Treatment Plant for Solids from Water Treatment
SSA-55 Sewage Treatment Plant (Northeast Section)
SSA-56 Sewage Treatment Plant (Northwest Section)
SSA-60 Rubble Pile East of Administration Building
SSA-63 C Line Boiling Tub House Settling Pits
SSA-64 Nitrocellulose C Line Collection Sump
SSA-65 Nitrocellulose A-B Line Acidic Water Settling Pits
SSA-66 Nitrocellulose A-B Line Neutral Water Settling Pits
SSA-67 Main Acid Sewer Pumps
SSA-70 Heavy Equipment Maintenance Shop Tractor Steam Cleaning Area
SSA-72 Oleum Plant Acidic Wastewater Sump
SSA-73 Main Lab Waste Container Storage Area
SSA-77 Garbage Incinerator
SSA-78 Rubble Pile Southwest of Unit 51
SSA-79 Asbestos Disposal Trench No. 2
SSA-80 Drainage Ditch for C Line Wastewater Treatment Plant Runoff
SSA-81 Red Water Treatment Plant